Infrastructure Expansion Plan

  • Road
    Road
    NO Project Name Project Content Period of Project Project Cost (100 million won) Remark
    1 Constructed Gwangyang-Jeonju Expressway 118.0㎞ 19,201 Completed
    2 Constructed Gwangyang Port Container Birth West Side Hinterland Road 11.4㎞ 2,030 Completed
    3 Constructed Yeosu-Gwangyang National Industrial Complex Access Road 8.5㎞ ‘05~’13 8,800
    4 Constructed Yeosu-Suncheon section of National Road No. 17 17.3㎞ 3,864 Completed
    5 Constructed Mokpo-Gwangyang Expressway 106.8㎞ 23,061 Completed
    6 Expand Deokyang-Sepo section of National Raod No. 22 22㎞ ‘08~’15 3,167
    7 Construct Yeosu-Goheung Peninsula Grand Bridge 38.3㎞ ‘01~’15 11,359
    8 Constructed Alternative Bypass for Woljeon-Sepung section of National Road No. 2 5.8㎞ 1,094 Completed
    9 Construct Alternative bypass for Sechung-Junggun section of National Road No. 2 9.6㎞ ‘05~’15 2,419
    10 Construct Bypass for Gwangyang-eup (Deoknye-Yonggan) section of National Road No. 2 6.1㎞ ‘04~’15 915
    11 Constructed South side access road for Yulchon Industrial Complex No. 1 3.0㎞ 434 Completed
    12 Constructed Shiindae main road for Sangsam-Woljeon 3.76㎞ 416 Completed
    13 Construct Alternative bypass for Jungheung-Hwangji section of National Road No. 17 13.2㎞ ‘07~’15 1,751
    14 Constructed Geum River-Dong Suncheon IC 1.86㎞ 250 Completed
    15 Construct Galsa-man Access Road No. 3 6.2㎞ ‘07~’15 932
    16 Construct Galsa-man Access Road (No. 1, 2 and 4) 7.8㎞ ‘08~’15 1,872
    17 Construct Main road and access road within Hwayang District 8.9㎞ ‘08~’14 670
    18 Construct Hanryro Grand Bridge for Yeosu-Namhae National Raod No. 77 6.0㎞ ‘08~’20 9,292
    19 Expand Hadong, Noryang- Jingyo local road 9.92㎞ ‘03~’15 616
    20 Construct Hadong Coast Road 19.4㎞ ‘01~’15 402
    21 Construct Haeryong Industrial Complex Access Road 1 Traffic square ‘12~’14 153
  • Railroad
    Railroad
    NO Project Name Project Content Period of Project Project Cost (100 million won) Remark
    1 Double tracked electrification of Iksan-Yeosu section of Jeolla Line 154.2㎞ 11,678 Completed
    2 Gwangyang Port container birth west side access railroad 7.0㎞ 1,690 Completed
    3 Improvement of railroad for Suncheon~Yeosu section of Jeolla Line 40.0㎞ 6,243 Completed
    4 Improvement of Dong Suncheon-Geangyang section of Gyeongjeon Line 10.9㎞ 2,533 Completed
    5 Connecting road with Yulchon Port 4.7㎞ 470 Completed
  • Airport and Seaport
    Airport and Seaport
    NO Project Name Project Content Period of Project Project Cost (100 million won) Remark
    1 Expanded Yeosu Airport 1.55㎞→2.5㎞ 900 Completed
    2 Build Gwangyang Port container berth 25선석 ‘87~’15 47,977
    3 Built the Gwangyang Port East Side Hinterland 2.54㎢(77만평) 3,794 Completed
    4 Built the Gwangyang Port West Side Hinterland 1.96㎢(59만평) 3,133 Completed
    5 Built the Gwangyang Port West Side Hinterland Road 11.4㎞ 3,030 Completed
    6 Build the 3rd stage spoilground for Gwangyang Port Revetment of 34.7㎞, etc. ‘02~’20 3,993
    7 Build Jungma General pier at Gwangyang Port 2선석 520 Completed
    8 Build the bridge for general pier for container berth of Gwangyang Port 교량 1개소 175 Completed
    9 Build the general container berth for Yulchon Industrial Complex No. 1 1선석 362 Completed
  • Water Supply and Drainage
    Water Supply and Drainage
    NO Project Name Project Content Period of Project Project Cost (100 million won) Remark
    1 Constructed wastewater treatment plant at Yulchon Industrial Complex No. 1 12,000㎥/day 226 Completed
    2 Constructed the water supply facilities at Shindae District 96,000㎥/day 270 Completed
    3 Constructed the drainage facilities at Chindae District 14,000㎥/day 117 Completed
    4 Construct the water supply facilities at Hadong District 57,000㎥/day ‘05~’20 2,556
    5 Constructed the water supply facilities at Hwayang District 8,000㎥/day 60 Completed
    6 Constructed the terminal disposal plant of sewage at Hwayang District 8,000㎥/day 568 Completed
    7 Support the installation of water supply facilities at Haeryong Industrial Complex 1 water distribution reservoirpipe line L=3.9㎞ ‘13~’14 60