Development Plan

본문내용

Container Berth Hinterland(East Side)

GWANGYANG

Promotion Status up to now

  • East Side
    • 2.54㎢(’03. 10. ~ ’08. 12.)
      • Work Section 1 ('03.10-'07.5.): 0.4km2 59.1 billion Won (MOLIT)
      • Work Section 2 ('05.5.-'08.11.): 1.22km2, 223.2 billion Won (MOLIT)
      • Work Section 3 ('06.5.-'08.12.): 0.33km2, 36 billion Won (Gwangyang City)
  • Operation Status
    • East Side Hinterland
      • 31 companies (Operation: 20, To be moved in: 11)
TOP