Development Plan

본문내용

Yulchon 1st Industrial Complex

GWANGYANG

Promotion Performance Up to Now

  • Progress Rate of Creation Work: 93% (1st Site:91%, 2nd Site: Completed)
    • Project Volume: Site creation (8.4million m2,) and road construction (26.0km) completed
    • Construction cost: 690.1billion Won (660billion Won by '13. 15.8 billion Won planned in '14, 14.3 billion Won after '14)
  • Parcelled Sale of created land: Land of 4.65million m2 (75.8%) among 6.14 million m2 was sold
    • Land for factory: 4.38m2, Land for support facility: 50,000m2, Land for distribution facility:220,000m2
        ※ Number of companies that are subjects of parcelled sale: 95 companies (Under operation: 64, Work started: 10, Work not started: 21)
  • Notification of partial completion permission : 6.21million m2 (67.7%) among 9.17 million m2
    • '11. December: 370,000m2 (4.0%), '12. August:5.33 million m2 (58.1%), '12. December: 510,000m2(5.6%)
  • 2nd Land (3.8million m2) completed: 2013. 12. 31

Future Promotion Plan

  • Creation of proposed port land as industrial land by changing its usage for expanded supply of industrial land
  • Project promotion based on goal of achieving 97% work progress in '14