Development Plan

본문내용

Seonwoel High-park Complex

SHINDEOK

Promotion Performance Up To Now

  • Conducting development intention survey: '11. 5-7
  • Notification of recruiting proposed developer: '11. 12. 30
  • Reception of application for designation for the project developer: '12. 2.29.
  • Main evaluation and selection of main preferred bidder: '12. 3. 29.
  • Conclusion of investment agreement (Chullanam-do, Suncheon city, Joonheung Const., Co., Ltd.): '12. 7. 24.
  • Pre-meeting for detailed enforcement agreement (5 times): '12. 8. - '13. 8.
  • Conclusion of detail enforcement agreement: '13. 9. 27.
  • Payment of performance bond (Joongheung Const., Ltd., -> GFEZ): '13. 10. 22.
  • Start of development plan and working design engineering :'13. end of October
  • Application for exception of District Designation Cancellation: '14. 1. 6.

Future Promotion Plan

  • Approval of development plan change (MOTIE): During May, '14.
  • Application for Approval of enforcement plan (Developer -> GFEZ): During August, '14.
  • Approval of enforcement plan, compensation and work start: During February, '15