Galsa Bay Shipbuilding Industry Complex

HADONG

Promotion Performance Up To Now

  • ’08. 9. 12 : Designation of projecct developer
  • ’10. 9. 28 : Concluded a contact of parcelled land sale with DSME [200,000 pyeong (660,000m2)]
  • ’12. 2. 29 : Concluded a construction contract with Hanshin E&C
  • ’12. 3. 20 : Started site preparation work of general test institute for marine plant
  • ’12. 5. 2 : Concluded a contract of parcelled land sale with Hadong-gun [100,000 pyeong (330,00m2)]
  • ’12. 5. 7 : Concluded PF loan agreement (Hadong-gun, Hagaedan, DSME, Hanshin E&C, Bookook Securities)
  • ’12. 8. 30 : Notification of changed approval of enforcement plan
  • ’12. 10. 9: Started construction of costal area (Light signallighted buoy: 6 sets, Silt Protector: 17km completed)
  • ’13. 2. 7 : Notification of changed approval of enforcement plan (Gwangyang Port Autority Notification No.:2013-2)
  • ’13. 2. 8 : Started revetment construction
  • ’13. 5. 20: Started dredging work (DSME site outfitting quay wall section: 1,722m)

Future Promotion Plan

  • ’15. 12월 : Completion of industrial complex creation