Development Plan

본문내용

Duwoo Leisure Complex

HADONG

Promotion Performance Up To Now

  • ’07. 12. 28 : Concluded MOU for development of 4 complexes of Hadong District
  • ’09. 02. 24 : Notification of compensation payment (650,000pyeong/27 billion Won paid among 680,000pyeong/29.9 billion Won)
  • ’09. 06. 05 : Notification of preferred bidder termination (Gyeongnam-do ->Hadong District SPC)
  • ’09. 09. 11 : Bidding announcement of project developer (No enterprise who submitted project proposal)
  • ’12. 02. 25 : Application for approval of GFEZ development plan (project period, cost) change (Gwangyang port authority ->MOLIT)
  • ’12. 03. 05 : Bidding announcement of project developer (Hadong-gun)
  • ’12. 06. 25 : Bidding announcement of project developer (No enterprise who was selected as preferred bidder)
  • ’12. 12. 17 : Notification of development plan change(’16~’20→’12~’16)
  • ’13. 04. 28 : Issue of PR material and letter of intent form for participation (270-odd companies)
  • ’13. 05. 16 : Visited PR to enterprises for investment attraction (5 companies: Geumho, Daemyeong, Hanhwa, Muju, Geumho E&C)
  • ’13. 11. 08 : Promotion plan of free economic zone restructuring (targeting the district excluded from designation release)
  • ’13. 11. 27 : Investment attraction by visiting enterprises (Gyeongnam Development Corporation, LH, Joongang Const., Co., Ltd.)

Future Promotion Plan

  • Extensive discovery effort of looking for potential investment company and PR activity (To be continued)
  • Request for exceptional zone from designation cancellation for free economic zone restructuring (Gyeongnam-do)
  • First half of '14: Bidding announcement of project developer