Development Plan

본문내용

Daesong Industrial Complex

HADONG

Promotion Performance Up To Now

  • ’08. 1. 24 : Designation of project developer (Hadong-gun, Daesong Industry Co., Ltd.)
  • ’12. 4. 5 : Issue of letter of intent for financing arrangement (Korea Investments & Securities ->Daesong Industry Co., Ltd.)
  • ’12. 12. 12 : Deposit of land compensation amount (15 billion Won) (Daesong Industry Co., Ltd. -> Hadong-gun)
  • ’12. 12. 18 : Notification of approval for development plan change
  • ’12. 12. 20 : Notification of approval for enforcement plan change
  • ’13. 2. 22 : Additional deposit of land compensation amount (5 billion won) (Daesong Industry Co., Ltd. ->Hadong-gun)
  • ’13. 4. 2 : Notification of land compensation (1.374million pyeong, 504 lots of land)
  • ’13. 5. 3 : Concluded PF loan agreement (181 billion Won, Hadong-gun, Daesong Industry, Korea Investments & Securities)
  • ’13. 6.19 : Application for approval of development plan change (authority ->MOTIE)
  • ’13. 7. 29 : Compensation consultation and payment notification (Compensation rate:89%, 847,000m2, 32.7 billion Won)
  • ’13. 10. 23 : Notification of approval for development plan change (MOTIE Gyeongjadan)
  • ’13. 11. 4 : Application for approval of development plan and enforcement plan change
  • ’13. 12. 13 : Concluded enforcement agreement (Hadong-gun, Daesong Industry Co., Ltd., Hanyang Corporation, Korea Investments & Securities)
  • ’14. 1. 8 : Notification of approval for development plan change (Gyeongsangnam-do)

Future Promotion Plan

  • Notification of approval for enforcement plan change
  • Creation of industrial complex to be completed by December, '16
TOP